DWP board approves $113,289 change order for Garstin facility, pushes firms on cost-sharing

Big Bear Lake Department of Water and Power commissioners voted 5-0 on Oct. 27 to approve added Garstin Water Operations Facility work, on the condition that staff talk to the design and soils firms about sharing the cost.

By Big Bear News2 min read1 source

Heading up the mountain? Road conditionsThis weekend

The Big Bear Lake Department of Water and Power board voted 5-0 on Oct. 27 to approve Change Order No. 03, worth $113,289.39, on the Garstin Water Operations Facility project. Approval is subject to a letter from the USDA State Engineer and to staff discussions with the project's design firm and geotechnical engineer about cost sharing for design oversights. Vice Chair Barbara Willey noted during the discussion that the project's remaining contingency stands at 2.9%, or $445,447.

Garstin change order

The newsletter

Get this in your inbox.

One email instead of six websites and a Facebook group. Weekdays plus a Saturday recap. Every claim cited. Tell us when something is missing.

No spam. One-click unsubscribe in every email.

Free to read, and staying that way. Subscribing helps fund a paid local reporter for the valley. Where the money goes.

Commissioner Joe Cylwik and Treasurer Craig Hjorth said they were disappointed the design firm did not anticipate the wall footing overexcavation and the added roof insulation that make up part of the change order, according to the minutes. Cylwik asked staff to approach both the design and soils firms about sharing those costs, and General Manager Reggie Lamson confirmed staff is "actively pursuing the matter."

Commissioner Matt Scriven asked what DWP is paying PBK in total, and CFO Nathan Statham answered approximately $800,000.

The change order also removes a snowmelt system at building entrances. Lamson said the entrances all have gables, which will reduce falling snow, and DWP will instead buy heated portable door mats to place at entrances during inclement weather. The minutes do not include any response from the design firm, the soils firm or the contractor.

Turf policy change

The board also voted 5-0 to adopt Resolution No. DWP 2026-09, amending its Water Conservation Policy No. 2014-02 on non-functional turf. Cylwik asked that the term "Non-Residential" be added throughout the policy text so the affected account types are explicit, and approval was made subject to that change.

Statham told the board that incorporating the state statute into DWP policy is mandatory. Water Conservation and Outreach Supervisor Bennett Rossell has already contacted the 13 DWP customers affected, and the policy covers all non-residential categories: commercial, institutional and industrial.

Other business

In management reports, District Engineer Daniel Baguyo said plans for Division Well No. 9 would be finalized the week of the meeting, with bidding expected within two weeks. Lamson said the project's scope has been reduced to improve cost efficiency.

After a closed session on the general manager's performance evaluation, the board reconvened and voted 5-0 to adopt Resolution No. DWP 2026-11, approving Amendment No. 2 to the 2025-2027 employment agreement with the general manager.

Whether the design and soils firms agree to share costs will determine how much of the change order DWP ultimately absorbs; the minutes record no timeline for those talks.

The newsletter

Get this in your inbox.

One email instead of six websites and a Facebook group. Weekdays plus a Saturday recap. Every claim cited. Tell us when something is missing.

No spam. One-click unsubscribe in every email.

Free to read, and staying that way. Subscribing helps fund a paid local reporter for the valley. Where the money goes.

Sources (1)

  1. 1.
    Big Bear Lake DWP Board meeting minutes, Oct. 27, 2026
    carried 5-0 to amend and approve Change Order No. 03 in the amount of $113,289.39 to the Facility Builders and Erectors, Inc. Contract for the Garstin Water Operations Facility Project subject to the letter of approval from the USDA State Engineer and DWP staff discussion with the design firm and geotechnical engineer regarding cost sharing for design oversights.
    Open original (opens in a new tab)

Report a problem

See a factual error? Tell us — we review every report before changing the story.

About: DWP board approves $113,289 change order for Garstin facility, pushes firms on cost-sharing

Tomorrow in Big Bear

  • Next event: Thanksgiving Weekend at Snow Summit · 8:00 a.m.
  • Sunrise: 6:31 a.m.
  • Next edition 7 AM